CC3800-1 performs its first lift in Australia

Premium Content

12 October 2020

124107_20200818_091039

NRW contracting commissioned Sarens to perform the crucial lift of rail bridge girders over operating railway track for Fortescue Metals Group’s Eliwana Project in the Pilbara, Western Australia. The entire operation of transporting two girders from the laydown area to the lifting location and installation had to be completed during the rail shut down window of an 8 hours access window.

The crane was imported and mobilised to the site in 3 weeks and assembled in 5 days. The other equipment used during the project were: 

  • LTM 1150
  • Two 6-Axle Line SPMT 
  • Two PPU

Two girders weighing up to 155T, were transported from the laydown area to the lifting position and lifted at a radius of up to 42m. The entire operation was safely completed by a crew of 8 members. According to Project Manager, Minhaj Rizvi, “The rail shutdown window of 8 hours was a challenge. Our team worked with meticulous planning and preparation and executed the lifts safely and efficiently within shutdown window with zero incidents.”

Latest News
Jekko Nederland now open for business
New subsidiary will operate in one of Europe’s most demanding markets
Repeatable movements: how to relocate an entire tower crane
Select Plant Hire’s new bolted lifting frame for tower crane relocation on the job site
Polaris completes road transport of oversized pressure filters
90-tonne units will be delivered to a customer in East Asia
CONNECT WITH THE TEAM
D.Ann Shiffler Editor, American Cranes & Transport Tel: +1 512 869 8838 E-mail: [email protected]
Alex Dahm Editorial Manager Tel: +44 (0) 1892 786206 E-mail: [email protected]
Mitchell Keller Managing Editor Tel: +1 (262) 483-3726 E-mail: [email protected]
Simon Battersby Sales Manager Tel: +44 (0) 1892 786223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA