Doing it differently

Premium Content

06 May 2008

One of the three inverter pots moved by Ainscough Engineering Services is taken from its housing in

One of the three inverter pots moved by Ainscough Engineering Services is taken from its housing in the walls of the Welsh steelworks

Steeling for removal in the UK, Ainscough Engineering Services, a separate company from Ainscough Crane Hire, but owned by the same family, was contracted to remove three inverter pots from the Llanwern Steelworks in Wales.

Ainscough used a 450 tonne capacity J&R 900 Series Lift & Lock hydraulic telescopic lifting system to remove the pots, which each weighed between 340 and 370 tonnes, and move them 6 m away from the surrounding steelwork before two

400 tonne capacity mobile cranes lowered them down completely.

Once the pots were clear of the steelwork and had been lowered by the mobile cranes, they were taken off site to be dismantled.

Latest News
CN Heavy Transport deploys new Scheuerle girder trailer
STB 260 transports large and heavy transformers in Norway
Gearmatic adds GM18 and GM50 hydraulic planetary winches
Two new winch models from USA-based manufacturer
MEC starts shipping first carry deck crane in North America
Company reports first shipment for new pick and carry crane
CONNECT WITH THE TEAM
D.Ann Shiffler Editor, American Cranes & Transport Tel: +1 512 869 8838 E-mail: [email protected]
Alex Dahm Editorial Manager Tel: +44 (0) 1892 786206 E-mail: [email protected]
Mitchell Keller Managing Editor Tel: +1 (262) 483-3726 E-mail: [email protected]
Simon Battersby Sales Manager Tel: +44 (0) 1892 786223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA