Heerema piles in

Premium Content

05 October 2018

Heerema's Aegir vessel at work

Heerema’s Aegir vessel at work

Increased efficiency, reduced cost and faster cycle times are among the benefits of a new method of installing piles for offshore wind turbines.

A new approach was taken by Heerema Marine Contractors, together with its client Delft Offshore Turbine (DOT) and their subcontractor Cape Holland. It was the installation of the DOT monopile at the Eneco Amalia wind park off the Dutch coast.

A relatively new driving technology was used by Cape Holland in combination with a new installation operation by Heerema’s offshore lift vessel Aegir, Heerema said. A Vibro Lifting Tool which is a hybrid of a vibro hammer and lifting tool was used to vibrate the monopile into the soil. It meant no other tools were needed for picking up, upending or finally driving the pile.

 

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

CONNECT WITH THE TEAM
D.Ann Shiffler Editor, American Cranes & Transport Tel: +1 512 869 8838 E-mail: [email protected]
Alex Dahm Editorial Manager Tel: +44 (0) 1892 786206 E-mail: [email protected]
Mitchell Keller Managing Editor Tel: +1 (262) 483-3726 E-mail: [email protected]
Simon Battersby Sales Manager Tel: +44 (0) 1892 786223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA