Helling in double act

Premium Content

17 September 2015

The LTR 1220 moves into the position at the rear of the LR 1600/2 and is attached to the derrick boo

The LTR 1220 moves into the position at the rear of the LR 1600/2 and is attached to the derrick boom

Crane contractor Helling, based in Schwäbisch Gmünd, southern Germany, used a Liebherr LTR 1220 telescopic crawler crane as counterweight for lowering, erecting and manoeuvring a LR 1600/2 lattice boom crawler crane.

Markus Helling, Helling managing director, worked with experts from Liebherr to develop the concept. Using the LTR 1220 as counterweight has a number of advantages, as Markus Helling explained, “I can save on eight transport units for the ballast, which is only required for the set-up process but not for the hoisting work in between – in other words for erecting and lowering the LR 1600/2 and each time it is moved.”

The concept was used during the erection of a Senvion wind turbine at a wind farm near the Rhine-Hesse town of Alzey. The turbine had a hub height of 128 metres.

Helling uses the LR 1600/2 to hoist the top steel tower sections onto prefabricated concrete towers and then to hoist the turbine sections. After assembling the rotor and completing the system on the previous day, the team from Helling started preparations to lower the crawler crane's lattice boom.

The boom included a 12 m fixed jib and had an overall length of 150 m. After dismantling the central ballast on the LR 1600/2, the LTR 1220 was moved behind the LR 1600/2 and positioned for use as counter-ballast. The LTR 1220 was then suspended on the derrick boom and was docked to the pulley head using an adapter on the rear of the 600 tonne LR 1600/2, a spokesperson said.

Once in position, the boom of the LR 1600/2 could be lowered. With that on the ground, the LTR 1220 is detached. The LR 1600/2 is fitted with a suspended ballast pallet. The LTR 1220 then holds the lattice boom of the LR 1600/2, allowing both cranes to be manoeuvred over the field to the next site, where it can be reassembled ready for the next lift.

It normally takes three and a half to four days to move the LR 1600/2 to the next site if the crawler crane has to be dismantled, transported and then erected again, a company spokesperson said. Using the LTR 1220 as a relocation aid, however, helped save Helling a large amount of time.

Latest News
Gearmatic adds GM18 and GM50 hydraulic planetary winches
Two new winch models from USA-based manufacturer
MEC starts shipping first carry deck crane in North America
Company reports first shipment for new pick and carry crane
Franc Jost 1938 to 2026
Saying goodbye to a prolific, long-serving and well-known tower crane designer
CONNECT WITH THE TEAM
D.Ann Shiffler Editor, American Cranes & Transport Tel: +1 512 869 8838 E-mail: [email protected]
Alex Dahm Editorial Manager Tel: +44 (0) 1892 786206 E-mail: [email protected]
Mitchell Keller Managing Editor Tel: +1 (262) 483-3726 E-mail: [email protected]
Simon Battersby Sales Manager Tel: +44 (0) 1892 786223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA