Responsive Image Banner

Mammoet lowers arena roof to complete dismantling

Premium Content

11 June 2020

The 2,250 tonne, 134 metre main truss of the Joe Louis Arena was lowered from an elevation of 25 metres to 6 metres

The 2,480 ton (2,250 tonne,) 440 foot (134 metre) main truss of the Joe Louis Arena was lowered from an elevation of 82 feet (25 metres) to 20 feet (6 metres).

A project to redevelop riverside land in the United States received assistance from Mammoet to lower the 440-foot (134 metre) long main truss of a redundant sports arena and complete its demolition.

The Joe Louis hockey arena is in the centre of downtown Detroit, MI, close to the United States-Canada border. What made the job tricky was its proximity to a metro centre and a large sewer main ran underground beneath the truss. It meant the demolition was a dismantling process rather than a traditional implosion.

Incorporated into the truss was the arena’s penthouse, helping to make it the largest component on the job. It was also the last to be removed. The original proposal was to take the steel and concrete truss apart a beam at a time.

Working for locally-based demolition contractor Adamo Group, Mammoet’s solution was to lower the entire truss in one piece for easier access to be dismantled on the ground. Another challenge in this approach was a narrow weather window due to the load’s large sail area.

Large beams were inserted under the truss so it could be lifted from its existing supports using eight strand jacks and then lowered onto supports. The truss was 82 feet (25 metres) up and Mammoet lowered it to 20 feet (6 metres) for cutting into more manageable chunks. Prior to the lift and lower operation two pairs of 7.9-foot (2.4 metre) tall girders, braced together, were put in to support the roof.

The steel and concrete truss was lifted to check its weight before the supports were cut away to allow lowering

The steel and concrete truss was lifted to check its weight before the supports were cut away to allow lowering

Without an accurate determination of the weight of the truss, it was lifted free in a way that would have allowed it to be put back had it been too heavy. On the day of the lift its weight was deemed acceptable so the ends were removed to allow it to be lowered past the original supports.

Multiple strand jacks on the one rigid structure demanded careful monitoring of the load on each jack to make sure the truss and the lifting equipment were loaded as designed. Within four hours of starting to lower, the Mammoet team of six had it lowered and set on the client’s shoring piles.

Richard Adamo, Adamo Group president, said, “I would recommend Mammoet to other contractors as they display real professionalism on the job. The team is very engaged and willing to overcome obstacles collectively and come up with solutions. With safety being of paramount importance on this project, and sensitive in nature due to the close watch of the public’s eye, Mammoet took all necessary precautions. It was a wonderful experience working alongside this team.”

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Latest News
Morrow’s Peter Juhren: top-notch leadership
D.Ann Shiffler catches up with Morrow Equipment’s Peter Juhren
Arrowhead Winch hosts first Authorized Service Center Advisory Council
Arrowhead Winch hosted its first Advisory Council meeting, bringing together 28 representatives from Authorized Service Centers to collaborate on offshore crane service standards. 
Berard Transportation marks 80 years with investment in next-gen fleet
Berard has expanded its fleet with 28 lines of TII-Scheuerle SPMT-ES trailers and two Z390 PPUs from Rigging Gear Sales. 
CONNECT WITH THE TEAM
D.Ann Shiffler Editor, American Cranes & Transport Tel: +1 512 869 8838 E-mail: [email protected]
Alex Dahm Editorial Manager Tel: +44 (0) 1892 786206 E-mail: [email protected]
Matt Burk VP Sales Tel: +1 773 610 9467 E-mail: [email protected]
Simon Battersby Sales Manager Tel: +44 (0) 1892 786223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

Your VIP Pass to the World Cranes & Transport Summit

Dublin | Nov 18–19
Cap off the Summit with an exclusive Super-Premium Irish Whiskey Tasting at the historic Swan Bar.
🥃 Network with industry leaders in an intimate setting
🌍 Gain world-class insights at the conference
🍀 Experience the culture of old Dublin

I'M INTERESTED