McDermott executes its heaviest lift
13 May 2024
USA-based energy sector engineering and construction solutions provider McDermott said it “successfully executed its heaviest stacking lift” at Jebel Ali fabrication yard in Dubai, United Arab Emirates, for an offshore wind power project in Germany.
The lift was made for the BorWin6 980MW high-voltage, direct current (HVDC) project for Dutch electrical transmission operator TenneT.
Six cranes were used to stack a deck level with a total weight of 1,962 tonnes (2,163 US tons). The tandem lift was led by McDermott’s lifting fabrication team with construction…