Osprey delivers 500 tonne reactor to Hinkley Point

Premium Content

EDF's reactor vessel on Osprey's Scheuerle SPMT Osprey used Scheuerle SPMT to deliver the 500 tonne reactor vessel. Photo: EDF Energy

The first of two nuclear reactors was delivered in February for the Hinkley Point C nuclear power station under construction for energy company EDF in the United Kingdom.

Following a journey by sea from France, where it was built by Framatome, the reactor arrived in the UK at Avonmouth Docks in Bristol, in the south west of England. It was then taken by barge to Combwich Wharf on the River Parrett in Somerset.

Final leg of the journey

Next was the final leg of the journey, a five hour overland trip of 4 miles (6.5 km) to the construction site. It was completed by Osprey Group using Scheuerle Generation 3 and Generation 4 self propelled modular transporter (SPMT). The reactor pressure vessel is 13 metres long and weighs 500 tonnes. The SPMT was set up in 4 file, 16 axle configuration, with two side by side columns of 16 axle lines for a total of 128 wheels. Two Z350 PPU (power pack units) were used, mounted at the rear, for traction.

Installation will be in the reactor building after the dome has been lifted in. The reactor creates the heat to make steam, for what will be the world’s largest turbines, EDF said. The last nuclear reactor delivered in the UK, also made by Framatome, was for the Sizewell B station which began operating in 1995.

The second of the two reactors will be handled and transported in the same way as the first one.

Latest News
Service in motion: new path for veterans in trucking
Initiative simplifies path for veterans to enter the industry
Faymonville Group sets up North American organisation
Faymonville Group North America will be based in Little Rock, Arkansas
Overhead crane collapse at Turkish steel plant kills 17
Details of the deadly 10 November crane collapse in Türkiye
CONNECT WITH THE TEAM
D.Ann Shiffler Editor, American Cranes & Transport Tel: +1 512 869 8838 E-mail: [email protected]
Alex Dahm Editorial Manager Tel: +44 (0) 1892 786206 E-mail: [email protected]
Mitchell Keller Managing Editor Tel: +1 (262) 483-3726 E-mail: [email protected]
Simon Battersby Sales Manager Tel: +44 (0) 1892 786223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA