Stacked with strands

Premium Content

06 May 2008

Construction of a new terminal for London's Heathrow Airport has been one of the UK's most high profile construction projects over the last year. Fagioli PSC was appointed lifting and transportation contractor by Watson Steel and was responsible for the erection of the new VCR Tower.

The 900 tonne conical top section of the tower was transported 2 km across a field to the site on three remote controlled six-axle self propelled modular transporters (SPMT).

Then, at the end of February, Fagioli PSC used three triangular 16 m towers and three L600 strand jacks to lift the top section 12 m, to allow tower segments to be installed, a process repeated until a final height of 87 m was achieved.

To stabilise the tower, Fagioli PSC supplied six L180 strand jacks in tension frames, three of which were simultaneously tensioned through the lifting jack control system software.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Latest News
Mammoet SPMT stars in bridge installation
Streamlined launch followed the Accelerated Bridge Construction (ABC) principle
Tadano AC 3.060-2 all terrain crane hits the market
Three axle 60 tonne AT with 50 metre boom built in Japan
Boss opens rail transload FTZ in Dayton, Texas
New addition offers ease of access for oversized loads
CONNECT WITH THE TEAM
D.Ann Shiffler Editor, American Cranes & Transport Tel: +1 512 869 8838 E-mail: [email protected]
Alex Dahm Editorial Manager Tel: +44 (0) 1892 786206 E-mail: [email protected]
Simon Battersby Sales Manager Tel: +44 (0) 1892 786223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA