Safe replacement of a 165-tonne ACC unit supports continued production at the factory

Sarens in Egypt recently carried out a heavy lifting operation at the Arabian Cement Factory in Ain El Sokhna, successfully replacing an ageing ACC unit with a new one.

The project was undertaken to ensure uninterrupted operations at the plant, as the old unit was nearing the end of its service life. Sarens was chosen for the task thanks to its proven capacity and qualifications to meet the client’s demanding requirements.

Planning & Equipment

During the planning phase, special attention was given to crane positioning and lift timing due to the tight space available at the factory site. Sarens deployed its CC4800 crane in SSL/LSL configuration with a 90m boom, selected for its ability to deliver the necessary lifting capacity at the required radius.

The crane was transported from the Sarens yard, taking one week to reach the site, followed by seven days of assembly. Despite the confined space, the equipment performed flawlessly throughout the operation.

The Lift

The scope included two picks in total: the removal of the old ACC and the installation of the new one. Each unit weighed approximately 165 tonnes and had to be lifted at a radius of 50m to a height of 32m. The tight crane position made manoeuvrability a challenge, requiring careful planning and execution.

The operation was carried out by a team of five Sarens specialists, working in close coordination with the client’s personnel. Over a period of ten days on site, the lifts were successfully completed, ensuring a safe and efficient replacement of the equipment.

A Turnkey Approach

This project highlights Sarens in Egypt’s ability to deliver complex technical solutions in challenging environments. By combining expertise in engineering, logistics, and lifting, Sarens once again demonstrated its capacity to provide clients with reliable, safe, and on-time project execution.

“Sarens had the right capacity and qualifications to meet the factory’s demands, and the team executed the job flawlessly,” said Essam Adel, Country Manager and Sales Manager at Sarens Egypt.

With this operation, Sarens in Egypt once again confirms its role as a trusted partner for heavy lifting and engineered transport solutions — delivering excellence for projects both large and small.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Latest News
Tadano all-terrain crane selected for fire service duty in Essen
New addition will support operations across a range of emergency scenarios
Kitchen’s Crane adds SPMT, gantry to fleet
Trio of machines added to Kitchen’s fleet
Mediaco acquires Paul Halbwachs
Company says crane rental company purchase is part of regional growth
CONNECT WITH THE TEAM
D.Ann Shiffler Editor, American Cranes & Transport Tel: +1 512 869 8838 E-mail: [email protected]
Alex Dahm Editorial Manager Tel: +44 (0) 1892 786206 E-mail: [email protected]
Simon Battersby Sales Manager Tel: +44 (0) 1892 786223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA