Site report IC January 2008, page 43.

Crane Rental Corporation in the US used two Manitowoc 2250 crawler cranes to tilt up and place boiler modules, weighing up to 190 tonnes each, at a power plant site in Florida.

Some text from the story was missing. It should have read that the lead crane had 169,200 pounds (75.5 tonnes) of crane counterweight and 60,000 pounds (26.8 tonnes) of carbody counterweight.

No luffing jib was used on the crane during the lift.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Latest News
Böcker electric crane completes construction project
Electrically-powered model was well-suited for use on city centre construction site
Ideas in action: Data centers, tariffs and AI top agenda at SC&RA Workshop
The 2026 workshop drew 753 attendees to Omaha, Nebraska.
Mammoet SPMT stars in bridge installation
Streamlined launch followed the Accelerated Bridge Construction (ABC) principle
CONNECT WITH THE TEAM
D.Ann Shiffler Editor, American Cranes & Transport Tel: +1 512 869 8838 E-mail: [email protected]
Alex Dahm Editorial Manager Tel: +44 (0) 1892 786206 E-mail: [email protected]
Simon Battersby Sales Manager Tel: +44 (0) 1892 786223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA