Final pier placed for Genoa bridge

Premium Content

24 February 2020

_FIL6890

The PerGenova team has completed the construction of all 18 piers for the new Genoa bridge

Salini Impregilo reports that a crucial stage of construction on the new Genoa bridge has been reached as, with its joint-venture (JV) partner Fincantieri, it has completed the installation of the structure’s 18th and final pier.

At the same time, the JV, known as PerGenova, undertook the raising of the first of the bridge’s three 94m-long decks. When completed, the bridge will carry 19 spans of deck, but the long spans have proved to be the most challenging for the project’s engineers.

The team ultimately decided against cranes and instead employed strand jacks to raise the 1,800-tonne spans, using cables to hoist them into position at a height of 40m.

In a release, Salini Impregilo said “All the vertical structures are in evidence, while the combined length of the horizontal spans has reached 500 out of a planned 1,067 metres”.

The company said there are approximately 600 people working on the project on a daily basis and encouraged people to visit the PerGenova website (www.pergenova.com) to follow their activities in real time.

The “highly symbolic” bridge is being built to replace the Morandi bridge, which collapsed in August 2018, killing 43 people.

PerGenova has committed to complete the new bridge by this summer.

Pietro Salini, CEO of Salini Impregilo, has previously said the PerGenova team would build “a hyper-technological bridge, sustainable because it is able to power itself, safe, delivered to the citizens in record time, and built in the first totally transparent construction site in the world, with webcams active 24 hours a day, seven days a week”.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Latest News
Arrowhead Winch hosts first Authorized Service Center Advisory Council
Arrowhead Winch hosted its first Advisory Council meeting, bringing together 28 representatives from Authorized Service Centers to collaborate on offshore crane service standards. 
Berard Transportation marks 80 years with investment in next-gen fleet
Berard has expanded its fleet with 28 lines of TII-Scheuerle SPMT-ES trailers and two Z390 PPUs from Rigging Gear Sales. 
Bridge installations working together in Hamburg
Teamwork made the bridge installation dream work and in much less time too
CONNECT WITH THE TEAM
D.Ann Shiffler Editor, American Cranes & Transport Tel: +1 512 869 8838 E-mail: [email protected]
Alex Dahm Editorial Manager Tel: +44 (0) 1892 786206 E-mail: [email protected]
Matt Burk VP Sales Tel: +1 773 610 9467 E-mail: [email protected]
Simon Battersby Sales Manager Tel: +44 (0) 1892 786223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

Your VIP Pass to the World Cranes & Transport Summit

Dublin | Nov 18–19
Cap off the Summit with an exclusive Super-Premium Irish Whiskey Tasting at the historic Swan Bar.
🥃 Network with industry leaders in an intimate setting
🌍 Gain world-class insights at the conference
🍀 Experience the culture of old Dublin

I'M INTERESTED