Heavy rotor transported in Saudi Arabia

Premium Content

04 February 2016

A rotor is replaced at Qurayyah power plant in Saudi Arabia

A rotor is replaced at Qurayyah power plant in Saudi Arabia

Teamlifting, a member of the Cargo Equipment Experts CEE network, replaced a 49.9 ton GT 11 generator rotor at the Qurayyah power plant in Saudi Arabia.

A 3 metre high structure was built to compensate for the 4.5 m height of the rotor axis above ground. Sliding beams were arranged on top of the structure for a distance of 20 m and specially prepared trolleys were used over these beams to pull out the rotor.

After removal, the rotor was transported by hydraulic low loader trailer to the ISCOSA (Siemens) workshop more than 80 kilometres away for repair. It was then taken back to the power plant and reinstalled, using the same jacking and skidding system.

Cargo Equipment Experts CEE is a global network of equipment owners, including haulers, crane operators, tug and barge operators, stevedores and export packers, port operators, rail operators, riggers and skidders, surveyors, air cargo handling equipment owners and supporting industry, serving the heavy and oversized cargo industry.

Latest News
Six Wolff cranes build Munich district amid active demolition
Tower cranes building alongside demolition in Germany
Tadano knuckle boom crane tackles US rail bridge repair
Crane navigated tight quarters between trees and power lines
McNally-Nimergood opens new branch in 80th year
In 80th year, USA-based firm opens new depot
CONNECT WITH THE TEAM
D.Ann Shiffler Editor, American Cranes & Transport Tel: +1 512 869 8838 E-mail: [email protected]
Alex Dahm Editorial Manager Tel: +44 (0) 1892 786206 E-mail: [email protected]
Mitchell Keller Managing Editor Tel: +1 (262) 483-3726 E-mail: [email protected]
Simon Battersby Sales Manager Tel: +44 (0) 1892 786223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA