Parking Space Solution

25 March 2008

Parking relief is on the way in downtown Orlando, FL, where a new seven-level parking garage is being built at Jefferson Street and Interstate 4. However, construction of the facility has been a headache due to congestion and tight working conditions - very little space to park a crane. To make the necessary lifts, some at a 200 foot radius, Crane Rental Corp. supplied its Link-Belt LS248H II rigged with 160 feet of working tower, 160 feet of luffing jib and a 30 foot fixed jib. Crane Rental provided the crane and an operator to the general contractor for the six months needed to complete the structure.