the numbers game

Premium Content

20 March 2008

MacArthur Maze

• 2,750 degrees F – heat of fire that melted steel beams that supported overpass

• 50 days – original estimate by state of California for how long repair would take

• 18 days – time it took C.C. Myers to rebuild roadway

• 100 tons – weight of newly fabricated concrete bent cap beam

• 25 days – time that roadway was closed $867,075 – Low bid submitted by C.C. Myers

• $200,000 - Incentive per day for early completion for early completion

• 3 – number of cranes that worked on the project from demolition to completion

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

CONNECT WITH THE TEAM
D.Ann Shiffler Editor, American Cranes & Transport Tel: +1 512 869 8838 E-mail: [email protected]
Alex Dahm Editorial Manager Tel: +44 (0) 1892 786206 E-mail: [email protected]
Matt Burk VP Sales Tel: +1 773 610 9467 E-mail: [email protected]
Simon Battersby Sales Manager Tel: +44 (0) 1892 786223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA