The 128 tonne top section is lifted onto the turbine mast

The 128 tonne top section is lifted onto the turbine mast

The project was to install two 5 MW wind turbine generators in 40 m deep water, 23 km off the North East coast of Scotland as part of a European Distant Offshore Wind Farms With No Visual Impact (DOWNVInD) project to establish the viability of large capacity wind turbine farms in deepwater and offshore locations.

Weldex was contracted to complete the onshore assembly and the first phase of the installation at Nigg. The company erected a support base in two sections, each weighing 125 tonnes. A 61 m, 230 tonne tower section was installed on the frame and the turbine components, totalling 734 tonnes. Once at the Beatrice Wind Farm site, a Weldex crane mounted on the Rambiz, a 3,300 tonne barge mounted crane operated by marine contractor Scaldis, assisted in the piling work to anchor the substructure in the seabed.

Latest News
Bauma China 2026 hails 21% increase in visitors
The number of visitors to Bauma China, which took place in Shanghai this week (23-27 November), increased 21%
5 big talking points from Bauma China 2026
Some of the major talking points from Asia’s biggest construction machinery trade show
Mammoet moves 3,700-tonne Hamburg railway bridge in one piece
The company says it set the 3,700-tonne structure in less than 24 hours.
CONNECT WITH THE TEAM
D.Ann Shiffler Editor, American Cranes & Transport Tel: +1 512 869 8838 E-mail: [email protected]
Alex Dahm Editorial Manager Tel: +44 (0) 1892 786206 E-mail: [email protected]
Mitchell Keller Managing Editor Tel: +1 (262) 483-3726 E-mail: [email protected]
Simon Battersby Sales Manager Tel: +44 (0) 1892 786223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA