Emergency transport

20 March 2008

Barnhart Crane and Rigging was called in to develop an emergency plan for mobilizing, hauling and in

Barnhart Crane and Rigging was called in to develop an emergency plan for mobilizing, hauling and installing a transformer in less than two weeks and a scant four days before the spring thaw embargo

On a cold winter night in Wisconsin in February 2006, American Transmission Co. (ATC) learned that a transformer had unexpectedly failed. Suddenly, a dreaded possibility now balanced on the edge of probability: blackout. It was an emergency situation.

The best and only real option was a spare transformer 40 miles away. But the move had to happen quickly as the spring thaw was quickly approaching and, when it arrived, heavy hauls would be restricted by the state.

ATC took matters into its own hands, contacting state and local governments, apprising them of the situation, and acquiring the vital permits. But then the plan was literally derailed. The original plan had the transformer being hauled by rail, but two weeks before the spring thaw, it was determined that it was too large to be transported by railcar. Through its general contractor, Kenny Construction, ATC's next call was to Barnhart Crane and Rigging.

Barnhart's planning team met ATC and Kenny Construction to formulate the over-the-road transport plan. By the end of the first day Barnhart crews went into action. The mobilization plan called for the use of a 12 dolly rig, and within 48 hours Barnhart crews began rigging for the removal of the replacement transformer.

Using a gantry system, the replacement transformer was removed and set onto a 10 line Goldhofer trailer for transfer to the dolly rig. Barnhart relocated the gantry to the dolly rig and offloaded the transformer. Quickly and thoughtfully, the Barnhart team completed the rig, and the transformer was roadworthy. Then on a clear night with temperatures hovering at 10 degrees F, and as the clock literally struck midnight, and just 10 days after receiving the call, Barnhart began hauling the replacement unit.

Barnhart Crane and Rigging was called in to develop an emergency plan for mobilizing, hauling and installing a transformer in less than two weeks and a scant four days before the spring thaw embargo

Utility crews and local authorities led the 40 mile trek. The schedule and planning was executed perfectly and the haul smooth and incident-free. By 9 a.m. the transformer was parked at the substation. Later, the unit was removed from the dolly rig and staged. The new transformer was then lifted with the gantry, set onto the Goldhofer trailer, and moved to location where it would be offloaded and set.

To put the transformer into place, the gantry was reset adjacent to the pad and Barnhart's slide track was constructed to move the transformer into its final home. Wisconsin Public Service Co. moved quickly to dress out, test and commission the transformer for ATC.