Sarens Performs Precision Replacements For TCO Turnaround Project In Kazakhstan

31 March 2024

Using extreme care, Sarens replaces reactors, column, and other elements at Tengiz facility

The TCO plant in Tengiz, Atyrau, Kazakhstan, recently contracted Sarens to help with turnaround works at the facility. By August 2023, Sarens Kazakhstan had successfully completed all critical work for the turnaround project, including replacing a D-503.2 column, which weighed 112 tonnes, and three reactors (R-720, R-721, and R-725) weighing 56 tonnes each. Sarens also designed and supported a variety of lifting works for the project, including the installation of transformers and the replacement of hard-to-reach pipelines.

As part of ongoing operations at the site, Sarens used 18 axle-lines SPMT as well as 14 cranes, including a Liebherr LR 1600-2 (600 tonnes), Sumitomo-SCX 1500A-3 (150 tonnes), and CC2400-1 crawler crane. The Liebherr and Sumitomo cranes were mobilised from Almaty while the other oversized cargo came from Atyrau and Aktau, 427 and 700 kilometres away, respectively. They remained on-site and operational for periods ranging from 25 through 60 days, and were configured in SLDB configuration with a 72-metre main boom and 260 tonnes SL counterweight.

As part of the turnaround operation, Sarens was tasked with replacing the most critical element: the 112-tonne column D 503. The column was more than 30 years old and lacked a proper lifting lug, which made the operation a challenge for the crew. To address this, Sarens Kazakhstan and the UK-based engineering team proposed using a needle beam to lift and remove it.

Sarens UK manufactures the needle beam specifically for this type of column, though installing it was still one of the most challenging parts of the operation. One working shift of twelve hours was needed to attach the new lifting tackles to the old column. To remove the old column and install the new one, Sarens then used a lift radius of 38 metres, completing the lifting work in less than half a day.

The team worked with extreme precision and care as they replaced the column, three reactors, and a variety of other elements. They had to manoeuvre around a narrow and congested working area that included overhead pipelines, trenches, manholes, light poles, and fire hydrants.

Finally, with the lifting work complete, Sarens project engineer Bassarov Kairat said, “Thanks to the professionalism of Sarens colleagues, all difficult tasks were completed on time and safely. This has helped earn more trust and respect from our client, TCO.”

Sarens would like to thank TCO for entrusting us with this important project, as well as the crew and colleagues who made the turnaround operation a success!

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Latest News
Longest turbine blades transported in Africa
New record for Vanguard with delivery of 25 turbines with 90 metre blades
Fagioli returns to UK market
Notus and Fagioli have a new joint venture business for heavy lifting and transport projects
Sönke Jordt strengthens fleet with Grove GMK4080L taxi crane
The taxi crane will support industrial, construction and infrastructure projects across northern Germany
CONNECT WITH THE TEAM
D.Ann Shiffler Editor, American Cranes & Transport Tel: +1 512 869 8838 E-mail: [email protected]
Alex Dahm Editorial Manager Tel: +44 (0) 1892 786206 E-mail: [email protected]
Matt Burk VP Sales Tel: +1 773 610 9467 E-mail: [email protected]
Simon Battersby Sales Manager Tel: +44 (0) 1892 786223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

Your VIP Pass to the World Cranes & Transport Summit

Dublin | Nov 18–19
Cap off the Summit with an exclusive Super-Premium Irish Whiskey Tasting at the historic Swan Bar.
🥃 Network with industry leaders in an intimate setting
🌍 Gain world-class insights at the conference
🍀 Experience the culture of old Dublin

I'M INTERESTED